Implementation of a project culture in Danish Graphene
HEBOproject is currently implementing a Project Management culture by establishing and leading a PMO function based on HEBOprojects own project management handbook tool. The task includes stage gate processes for project management, product development and Agile technology development.
The task is also to set up project governance by leading steering committees, ensuring project quality through project reviews prior to gate meeting and ongoing hiring and coaching of project managers. Finally project portfolio and resource management is also part of the assignment.
HEBOproject is part of the management team representing the PMO function on a weekly basis which is a great way to implement the new methods and tools.
HEBOproject also supports Danish Graphene by leading a newly won EUDP funded project on advanced graphene production technologies.
Customer: siemens and european energy
power2x hydrogen and battery energy storage epc project – kragerup estate
Year: 2025
HEBOproject managed the development, planning and construction (EPC) of one of the first scaled Power2X facilities able to produce green hydrogen and store electricity from the Danish grid. The site is located at Kragerup Estate on Zealand in Denmark.
The facility consists of wind turbines, batteries, an electrolyzer + BoP and finally an advanced controller system. The aim is to demonstrate the ability to optimize the utilization of wind energy to produce hydrogen and support the grid when needed.
HEBOproject had the role as project director for the turnkey project at the Siemens location and managed all internal stakeholders, resources as well as external parties involved in the project.
During construction Siemens decided to sell the project and HEBOproject managed the sale and transition of the project to energy developer European Energy. After the contract was signed HEBOproject supported European Energy to reach COD.
Customer: Siemens Wind Power
Gunfleet Sands 3 Demo Wind Farm – Offshore in the UK
Year: 2012
Responsible project manager for the engineering, procurement and construction of the first prototypes of the, at that time world’s largest, 6 MW wind turbines offshore. The project was executed in partnership with DONG Energy and A2SEA and their new build installation vessel – Sea Installer.
A pioneer project which required the ability to structure the many unknowns and challenges in such an innovative project across Europe with teams in Denmark, Germany and the UK.
Financial responsibility > 20.000.000 EUR
International team size > 50 persons
Customer: Eltronic Wind Solutions
Implementation of a Global Project Management Office
Year: 2017
Established an international project management department including processes with profit & loss responsibility for 50 international projects and a project portfolio with a total budget of 250 mDKK.
Recruited and led a team of 10 project managers and project coordinators. Introduced new processand created transparency in the project portfolio.
Customer: Siemens Wind Power
Anzetel Wehlens test Wind farm
Year: 2014
Responsible project manager for the engineering, procurement and construction of the first 6 MW prototype wind turbines in Germany for Bio Energie Nord. The largest turbines installed in Germany with a total height of 195 meters. The turbines were made for offshore deployment but sold to an onshore test park and therefore presented huge challenges during transport and lifting due to their size.
Financial responsibility > 20.000.000 EUR
International team size > 50 persons
Customer: Siemens Wind Power
Education program for Project employees
Year: 2011
Developed, trained and evaluated up to 100 project managers, project participants and steering committee members through multi day programs.
The trainings were done off site with various role plays to simulate real project challenges for the participants. All trainings were followed up by on-the-job evaluations and coaching session to ensure implementation.
This program was done in partnership with Volk Education with whom HEBOproject has close collaboration with through many years.
Customer: Siemens Wind Power
Hywind Scotland – Worlds first floating offshore wind farm
Year: 2015
esponsible project manager. Completed the planning phase of the engineering, procurement and construction of 5 x 6MW floating wind turbines erected on floating foundations in Norway and towed to Scotland for anchorage.
Financial responsibility > 50.000.000 EUR
International team size > 50 persons
References
What people say
about Hebo Project
contact
Let’s work together
Whether you are looking for urgent support on a specific project, need consulting on optimizing or structuring your project business or an interim manager in a project department, HEBOproject can assist you.
Do not hesitate to contact me to discuss your specific project needs.
Henrik Bonde – Owner